The Friday Report - 7/25/14

Posted by admin on July 25, 2014

July 25, 2014 TMS Pre-production Report...updated July 27

Wilkinson County:

Halcon Blackstone 4H-2, located roughly halfway between Centreville and Woodville on the south side of Hwy 24...The last few plugs are being drilled out now...A work over rig was brought in to finish the job started with a coiled tubing unit. Flow back and first production will likely be in August.

Halcon Fassman 9H-1, truck access road is located off Hwy 61 onto Sam Leake Road, then to Whetstone. H&P Flex3 Rig # 623 spudded May 29. Drilling complete and rig moved to Shuckrow.

Halcon Shuckrow 10H-1, located on Sam Leake Road about 5 miles east of Hwy 61, H&P Rig # 623, moving on site...should spud this week.

Halcon S D Smith, located on the Jackson Louisiana Road south of Woodville. H&P Flex 3 Rig# 249 spudded June 9, 2014. Drilling away with some delays.

Goodrich CMR Foster Creek 24-13, access from Hwy 24 on Hiram McGraw Road to Macedonia Road, then to end of Helmer Road. Nabors Rig # 624 spudded May 30. No report this week...Expected this rig to move to the CMR-Foster Creek 8H site when finished.

Goodrich CMR/Foster Creek 31-22H-1, access from Hiram McGraw Road off of Hwy 24. Nabors X-17, Spudded July 8. Drilling away.

Sanchez Dry Fork Creek # 2H, RAPAD Rig # 31 spudded May 21, 2014. Drilling completed to 18,200', then, according to Sanchez news release Wednesday, "...During clean out prior to running production casing, the drill string parted due to defects in the drill pipe. We are now in the process of sidetracking the lateral portion of the well and expect to have casing run within two weeks..." St. Davis #1 site located on Kahnville Road south of Gloster, MS awaiting Rig # 31 arrival.

EnCana Pintard 28H-2, located roughly 3 miles north of Centreville off Macedonia Road- Trinidad Rig # 124 finished drill with 20,807' total depth and an approximate lateral length of 8,500'....Rig moved to Ash 13 in Amite County. Should begin frac operations when Lyons 35H-2 frac job is completed.

Comstock CMR Foster Creek 28-40 No. 1H, located on Will Floyd Road, Access appears to be south off of Hwy 563 on to Dry Fork Creek Road, then on to Will Floyd Road. Site ready, rig coming soon.

Amite County:

Sanchez St. Davis #1, accessed from Hwy 24 in Gloster, located down Kahnville Road about 6 miles southeast of Gloster. Expect RAPAD Rig # 31 to locate on site spud, begin drilling in a couple of weeks.

Encana Ash 13H-1 and 13H-2, Located on the east side of Ash Road, accessed via Lower Centreville Road about 3 miles southeast of Centreville. Trinidad Rig # 124 spudded July 21.

Encana Lewis 7-18H-1, located about 1 mile north of the Lower Centreville Road off of the County Farm Road roughly 7 miles south of Liberty. Twenty-nine successful fractures, 8,000' lateral. Flow back started July 14, first sale July 19...early signs indicate a very good well.

Encana Lyons 35H-2- Located on same site as Lyons 35H-1, Trinidad Rig # 125 - drill reportedly completed around June 11 with about a 5,000' lateral. Frac operations underway by FTS, International (aka Frac Tech).

Encana Sabine 12H-1 and 12H-2, located off of Enterprise Road, south of Hwy 24 about 3 miles out of Liberty, access is from Hwy 48. Trinidad Rig # 125 spudded 12H-1 on June 20 and 12H-2 on June 23. Core samples being taken.

EnCana Mathis 29-32H-1, Located on the Louisiana line due south of the Anderson 17H unit, just off of Bean Road in T1N, R5E. Well completed and flowing back. Appears to be a very good well.

Goodrich Spears 31-6H-1, Located on the recently completed C H Lewis site pad on the west side of Bates School Road north of Gillsburg. Ensign Rig #753 is rumored to have spudded Friday, July 18 and is drilling away.

Goodrich Bates 25-24H-1, located roughly 2 miles northeast of Liberty off of Hwy 569 North. No word on lateral length, but I am expecting 5,000' or more. Frac operations should follow completion of the Denkmann.

Goodrich Denkmann 33-28H-2, located in Amite County on the Mississippi/Louisiana line in T1N, R4E. Accessed from the Louisiana side through Weyerhaeuser roads off of Tolar Hurst/Parish Road 181 off of Hwy 1044 north of Hwy 38. Halliburton doing a frac job now.

St. Tammany: Permit pending

Washington Parish: Permits pending

Tangipahoa: Pads ready and in process. Permits pending.

St. Helena Parish: Permits pending.

East Feliciana: Permits pending

West Feliciana:

Goodrich SLC 81H-1- Ensign Rig #751. Located off of Walker Road via LA Hwy 421 north of and about 12 miles from Jackson, LA. Flowback started...high hopes.

Halcon Walker drill, previously scheduled, has been delayed.