TMS PRE-PRODUCTION UPDATE 11-28-2014

Wilkinson County:
 
Halcón George Martens 1H
, located on the west side of the south lane of Hwy 61 south of Woodville a couple of miles. Spud 8-8-2014 and completed around the 8th of September.  Flowing back.


Halcon Creek Cottage West 1H, H&P Flex 3 Rig #249 completed drilling. Creek Cottage is located on Whitestown Road a couple of miles south of Hwy 24.  Fracturing should be taking place soon.

Halcon Rogers 1H, accessed from Hwy 24 west of Centreville about 5 miles.  H&P Flex Rig # 249 spud (began drilling) 10-23-2014. Drilling operations are complete and the H & P Flex Rig # 249 has left the TMS.

Goodrich CMR-Foster Creek 8-H-1 and 2, access from 24 on Hiram McGraw Road to Macedonia Road, then a mile or so down Helmer Road. Nabors Rig #624 spud -1 on 9-15 and spud -2 on 9-21.  Drilling away...#1 finished, working on #2.
 
Comstock CMR Foster Creek 28-40 No. 1H, located on Will Floyd Road. Access appears to be south off of Hwy 563 on to Macedonia Road, then on to Netterville Road, then on to Will Floyd Road. Trinidad Rig #103 began drilling on August 14.  Drilling operations have finished and the rig appears to be moving to the CMR Foster Creek 30-31 #1H site around the corner.

Comstock CMR Foster Creek 30-31 #1H, should be hosting the Trinidad Rig # 103 shortly.

Sanchez Morris 1H, RAPAD Rig #31 spud October 13.  Accessed from the Pickneyville Road...Traveling west out of Woodville, turn north (right) just past the Old River water tank on to an otherwise private road. (Unless you have business at the oil site, please respect the privacy rights of the landowner.) Drilling completed. 

The Bloomer 1H was reportedly next, but Bloomer remains unpermitted and the site has not been completed.  Meanwhile the Macedonia site north of Centreville appears ready to go, except for enlargement of a water holding pond, which is in process. I'm guessing RAPAD Rig #31 is headed to the Macedonia.

Sanchez Macedonia (2 wells are permitted...the -1, -2, and another, -4, is applied for...) 2 wells planned for drilling.  Macedonia is located on Macedonia Road north of Centreville.  Likely accessed south off of Hwy 563 with the site on the west side of Macedonia Road just north of Macedonia Methodist Church.
  
Amite County:.

Sanchez St. Davis #1, accessed from Hwy 24 in Gloster, located down Kahnville Road about 6 miles southeast of Gloster.  This well was drilled above the rubble zone in what may be a TMS record time of about 24 days with a lateral of 5,600’.  Flowing back.  We will have to wait on a required report to the Mississippi Oil and Gas Board to determine how good of a well it is.

Encana Ash 13H-1 and 13H-2, Located on the east side of Ash Road, accessed via Lower Centreville Road about 3 miles southeast of Centreville. Trinidad Rig #124 spud July 21.  Fracking operations continue.

Encana Sabine 12H-1 and 12H-2, located off of Enterprise Road, south of Hwy 24 about 3 miles out of Liberty, access is from Hwy 48. Trinidad Rig # 125 spudded 12H-1 on June 20 and 12H-2 on June 23. These wells are flowing back and began producing very early in the process.  Signs suggest two good wells.

Goodrich T. Lewis 7-38H-1 located from the same access road as the EnCana Lewis 7-18H-1 off of County Farm Road a mile or so north of the Lower Centreville Road, accessed off of the Greensburg Road, located about 6 miles south of Liberty.  Ensign Rig #753 reportedly spud on November 14. Drilling away...intermediate set.
 
Encana Longleaf 29H-1 and -2, located off Tobias Lane off of Hwy 584 roughly 3 miles southeast of Liberty. Trinidad Rig # 125 spud -2 on September 30 and -1 on 10/4.  -2 has completed drilling.  Word is -1 could be finished soon, if not already.

Encana Mathis 29-17H-1, located on the same pad as Mathis 29-32H-1 off of Bean Road west of Gillsburg in south Amite County.  Trinidad Rig # 124 spud October 17. Completed a 9,169 foot lateral drill to a total depth of 21,730 foot on or before November 25.

EnCana Lawson 25-13H-1, located on the same pad as the Lawson 25H-1 in Downtown Gillsburg, MS in Southeast Amite County should be hosting Trinidad Rig #124 shortly.

Pike County: A permit has been approved for 1 Sanchez unit and is pending for 2 units applied for by both Sanchez and VirTex.

St. Helena Parish:

Comstock Meeks 56 HZ-1, located on Martin Lane north of Hwy 38 off of Hwy 441, just south of the Mississippi line and the Encana Lawson 25H-1.  Trinidad Rig # 103, now located in Wilkinson County, is scheduled for this site once 2 wells are completed in Wilkinson County.

St. Tammany: Permit pending.

Washington Parish: Permits pending, site preps completed.  Note the latest permitted unit in Tangipahoa Parish, the Goodrich B-Nex 43H-1, will nose over into Washington Parish.

Tangipahoa:

Goodrich Verberne 5H-1, located south of Hwy 38 on Hwy 1061. Nabors X-17 spud 8-25.  Completed total drill of 18,938 foot. Fracking operations completed with 20 of 21 stages successfully fractured.

Goodrich Williams 46H-1 has the Ensign Rig #753 spud 9/11. Completed total drilling depth of 18,650 foot. Fracturing 20 stages.  Fifteen completed successfully, so far.

Halcon Franklin PST Prop H-1, H&P rig # 623 spud November 1. Access to this site is from downtown Osyka, Mississippi on South Railroad. As of November 24, drilled to 16,230’, but experienced issues with hole integrity.  Backed off to 13,880’ and working to restore the hole.

Goodrich Kent 41H-1, Nabors X-17, located on Monroe Stevens Road, accessed via Hwy 440/1057 to Hwy 1058 to B Brown Road, then to Monroe Stevens Road. Spud November 5.  Cemented intermediate in place and drilling away at 11,853’ as of November 24.

East Feliciana: Permits in process…

West Feliciana:

Halcon Walker drill, previously scheduled, has been delayed. 